| Phase 1 Construction - 26th January 2009 | |
|---|---|
| Substructure and Frame | 9th February – 3rd July |
| External Envelope (walls, windows etc) | 15th June – 16th October |
| Internal | 15th June – 18th December |
| External Works ( drainage, landscaping west car park) | 2nd March – 11th December |
| Building Handover - 18th December 2009 | |
| Phased Migration to New Building | 5th January – 15th January 2010 |
| Phase 2 - 18th January 2010 | |
| Block B demolition and secure car park construction | 18th January 2010 – 28th June 2010 |
| Project Completion - 28th June 2010 | |