Project Programme

Phase 1 Construction - 26th January 2009
Substructure and Frame 9th February – 3rd July
External Envelope (walls, windows etc) 15th June – 16th October
Internal 15th June – 18th December
External Works ( drainage, landscaping west car park) 2nd March – 11th December
Building Handover - 18th December 2009
Phased Migration to New Building 5th January – 15th January 2010
Phase 2 - 18th January 2010
Block B demolition and secure car park construction 18th January 2010 – 28th June 2010
Project Completion - 28th June 2010